Georgia Power demolishes homes for AI data center transmission lines
Georgia Power is demolishing between 20 and 30 homes in rural Georgia to build transmission lines that will primarily serve AI data centers, displacing homeowners through eminent domain. Residents describe the process as harmful to their families and communities, with limited legal recourse beyond challenging compensation amounts.
What happened
Georgia Power is demolishing between 20 and 30 homes across Coweta and Fayette counties to build high-voltage transmission lines serving AI data centers. The utility estimates that 70-80% of capacity on the new transmission line will serve data centers, with the remaining 20-30% serving residential and commercial demand. About 330 private properties sit in the path of the project.
Homeowners including Angela Hall, who purchased her home in 2003 through a USDA loan program for single mothers in rural areas, are being forced to sell through eminent domain or face involuntary takings. Her daughter Ansley Brown has publicly stated that Georgia Power is "taking it by force" and that homeowners have no choice in the matter.
Reported impact
Residents describe the forced displacement as harmful to their families and communities. Brown stated: "You can't tear down 35 miles of rural Georgia and it not hurt something or somebody. And to say that you're doing it in the name of data centers is a slap in the face to us, our community, our animals."
Index analysis
Georgia Power is building new transmission capacity to support at least four AI-focused data centers. The company says increasing demand has outpaced the capacity of its existing grid, requiring acquisition of over 300 parcels including residential properties.
Governance controls
Homeowners' legal options are limited to challenging compensation valuation, as eminent domain is a legal process that allows private property to be taken for projects determined to serve a public purpose. Georgia Power stated that eminent domain is "always a last resort" and that it feels it has conducted the process responsibly.
Classification
Sources and evidence
Sources not yet published
This record was researched and written by the Index from original reporting. Its sources are still being verified by an editor, and they are listed here once that check is complete. Until then the record carries no reviewer.